Robust planning in optimization for production system subject to random machine breakdown and failure in rework. (English) Zbl 1177.90107

Summary: This study is concerned with robust planning in optimization, specifically in determining the optimal run time for production system that is subject to random breakdowns under abort/resume (AR) control policy and failure in rework. In most real-life production processes, generation of defective items and breakdowns of manufacturing equipment are inevitable. In this study, random defective rate is assumed and all manufactured items are screened. The perfect quality, reworkable and scrap items are identified and separated; failure-in-rework is assumed. The system is also subject to random machine breakdown; and when it occurs, the AR policy is adopted. Under such policy, the production of the interrupted lot will be immediately resumed when the machine is restored. Mathematical modeling and derivation of the production-inventory cost functions for both systems with/without breakdowns are presented. The renewal reward theorem is used to cope with the variable cycle length when integrating cost functions. The long-run average cost per unit time is obtained. Theorems on convexity and on bounds of production run time are proposed and proved. A recursive searching algorithm is developed for locating the optimal run time that minimizes the expected production-inventory costs. A numerical example with sensitivity analysis is provided to give insight into the optimal operational control of such an unreliable system.

MSC:

90B25 Reliability, availability, maintenance, inspection in operations research
90B30 Production models
90B10 Deterministic network models in operations research
PDFBibTeX XMLCite
Full Text: DOI

References:

[1] Harris, F. W., How many parts to make at once, Factory, The Magazine of Management, 10, 135-136 (1913)
[2] Silver, E. A.; Pyke, D. F.; Peterson, R., Inventory management and production planning and scheduling (1998), Wiley: Wiley New York, p. 151-72
[3] Zipkin PH. Foundations of inventory management, vol. 476. New York: McGraw-Hill Co.; 2000. p. 30-60.; Zipkin PH. Foundations of inventory management, vol. 476. New York: McGraw-Hill Co.; 2000. p. 30-60.
[4] Nahmias, S., Production & operations analysis (2005), McGraw-Hill Co: McGraw-Hill Co New York, p. 183-205
[5] Osteryoung, S.; Nosari, E.; McCarty, D.; Reinhart, W. J., Use of the EOQ model for inventory analysis, Production and Inventory Management, 27, 39-45 (1986)
[6] Barlow, R. E.; Proschan, F., Mathematical theory of reliability (1965), Wiley: Wiley New York · Zbl 0132.39302
[7] Rosenblatt, M. J.; Lee, H. L., Economic production cycles with imperfect production processes, IIE Transactions, 18, 48-55 (1986)
[8] Lee, H. L.; Rosenblatt, M. J., Simultaneous determination of production cycle and inspection schedules in a production system, Management Sciences, 33, 1125-1136 (1987) · Zbl 0628.90032
[9] Bielecki, T.; Kumar, P. R., Optimality of zero-inventory policies for unreliable production facility, Operations Research, 36, 532-541 (1988) · Zbl 0652.90054
[10] Posner, M. J.M.; Berg, M., Analysis of a production-inventory system with unreliable production facility, Operations Research Letter, 8, 339-345 (1989) · Zbl 0682.90048
[11] Zhang, X.; Gerchak, Y., Joint lot sizing and inspection policy in an EOQ model with random yield, IIE Transactions, 22, 41-47 (1990)
[12] Hariga, M.; Ben-Daya, M., Note: the economic manufacturing lot-sizing problem with imperfect production processes: bounds and optimal solutions, Naval Research Logistics, 45, 423-433 (1998) · Zbl 0941.90027
[13] Hayek, P. A.; Salameh, M. K., Production lot sizing with the reworking of imperfect quality items produced, Production Planning and Control, 12, 584-590 (2001)
[14] Chiu, S. W.; Gong, D. C.; Wee, H. M., The effects of the random defective rate and the imperfect rework process on the economic production quantity model, Japan Journal of Industrial and Applied Mathematics, 21, 3, 375-389 (2004) · Zbl 1080.91048
[15] Jamal, A. M.M.; Sarker, B. R.; Mondal, S., Optimal manufacturing batch size with rework process at a single-stage production system, Computers & Industrial Engineering, 47, 77-89 (2004)
[16] Chiu, Y. P., Determining the optimal lot size for the finite production model with random defective rate, the rework process, and backlogging, Engineering Optimization, 35, 4, 427-437 (2003)
[17] Chiu, Y-S. P.; Lin, H.-D.; Cheng, F.-T., Optimal production lot sizing with backlogging, random defective rate, and rework derived without derivatives, P I Mech E Part B: Journal of Engineering Manufacture, 220, 9, 1559-1563 (2006)
[18] Chiu Y-SP. The effect of service level constraint on EPQ model with random defective rate. Mathematical Problems in Engineering 2006 (Article ID 98502) 13, doi:10.1155/MPE/ 2006/98502.; Chiu Y-SP. The effect of service level constraint on EPQ model with random defective rate. Mathematical Problems in Engineering 2006 (Article ID 98502) 13, doi:10.1155/MPE/ 2006/98502. · Zbl 1200.91154
[19] Groenevelt, H.; Pintelon, L.; Seidmann, A., Production lot sizing with machine breakdowns, Management Sciences, 38, 104-123 (1992) · Zbl 0759.90039
[20] Abboud, N. E., A simple approximation of the EMQ model with Poisson machine failures, Production Planning and Control, 8, 4, 385-397 (1997)
[21] Cheung, K. L.; Hausman, W. H., Joint determination of preventive maintenance and safety stocks in an unreliable production environment, Naval Research Logistics, 44, 3, 257-272 (1997) · Zbl 0890.90070
[22] Kim, C. H.; Hong, Y.; Kim, S-Y., An extended optimal lot sizing model with an unreliable machine, Production Planning and Control, 8, 6, 577-585 (1997)
[23] Moinzadeh, K.; Aggarwal, P., Analysis of a production/inventory system subject to random disruptions, Management Science, 43, 11, 1577-1588 (1997) · Zbl 0902.90048
[24] Chung, K. J., Bounds for production lot sizing with machine breakdowns, Computers & Industrial Engineering, 32, 139-144 (1997)
[25] Kuhn, H., A dynamic lot sizing model with exponential machine breakdowns, European Journal of Operational Research, 100, 3, 514-536 (1997) · Zbl 0918.90080
[26] Dohi, T.; Kaio, N.; Osaki, S., Minimal repair policies for an economic manufacturing process, Journal of Quality in Maintenance Engineering, 4, 4, 248-262 (1998)
[27] Makis, V.; Fung, J., An EMQ model with inspections and random machine failures, Journal of the Operational Research Society, 49, 1, 66-76 (1998) · Zbl 1111.90317
[28] Liu, B.; Cao, J., Analysis of a production-inventory system with machine breakdowns and shutdowns, Computers & Operations Research, 26, 73-91 (1999) · Zbl 0957.90005
[29] Boone, T.; Ganeshan, R.; Guo, Y.; Ord, J. K., The impact of imperfect processes on production run times, Decision Sciences, 31, 4, 773-785 (2000)
[30] Chung, K. J., Approximations to production lot sizing with machine breakdowns, Computers & Operations Research, 30, 1499-1507 (2003) · Zbl 1039.90014
[31] Giri, B. C.; Dohi, T., Exact formulation of stochastic EMQ model for an unreliable production system, Journal of the Operational Research Society, 56, 5, 563-575 (2005) · Zbl 1095.90024
[32] Lin, G. C.; Kroll, D. E., Economic lot sizing for an imperfect production system subject to random breakdowns, Engineering Optimization, 38, 1, 73-92 (2006)
This reference list is based on information provided by the publisher or from digital mathematics libraries. Its items are heuristically matched to zbMATH identifiers and may contain data conversion errors. In some cases that data have been complemented/enhanced by data from zbMATH Open. This attempts to reflect the references listed in the original paper as accurately as possible without claiming completeness or a perfect matching.